Amendment on Thermal Power Plants-Gazette Notification G.S.R. 446(E) dated 03.07.2025

Notification, 2025

A notification made under the The Environment (Protection) Act, 1986.

Kind Notification Year 2025 Jurisdiction Central Ministry Environment, Forest and Climate Change Text 2,000 characters

Made under The Environment (Protection) Act, 1986.

Source document (PDF, 1.9 MB)

Text

Reproduced from the document India Code holds for this instrument. The Gazette prints Hindi and English side by side and this is the English; the Department's own PDF remains the authority.

EXTRAORDINARY

PUBLISHED BY AUTHORITY

No. 403] NEW DELHI, THURSDAY, JULY 3, 2025/ASHADHA 12, 1947

MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE

NOTIFICATION

New Delhi, the 3rd July, 2025

G.S.R. 446(E).—Whereas, the draft of certain rules to amend the Environment (Protection) Rules, 1986 was published as required under sections 6 and 25 of the Environment (Protection) Act,1986, vide notification of the Government of India in the Ministry of Environment, Forest and Climate Change number

G.S.R. 121(E), dated the 7th February, 2025, inviting objections and suggestions from all persons likely to be affected thereby and notice was given that the said draft shall be taken into consideration on or after expiry of sixty days from the date of publication in the official Gazette; And Whereas, objections and suggestions received from all persons and stakeholders in response to the aforesaid notification have been duly considered by the Central Government; Now, therefore, in exercise of the powers conferred by sections 6 and 25 of the Environment (Protection) Act, 1986 (29 of 1986), the Central Government hereby makes the following rules to further amend the Environment (Protection) Rules, 1986, namely: -

1. Short title and commencement.—(1) These rules may be called the Environment (Protection) Third Amendment Rules, 2025.

(2) They shall come into force on the date of their publication in the Official Gazette.

2. In the Environment (Protection) Rules, 1986, in Schedule - I, against serial number 5A, in column 4, after item II, the following proviso shall be inserted, namely: - “Provided that the Ministry may, in consultation with the Central Electricity Authority and the Central Pollution Control Board, for reasons to be recorded in writing by an order grant exemption to thermal power plants from installation of Cooling Towers”.

[F. No. Q-15017/40/2007-CPW (part)] NEELESH KUMAR SAH, Jt. Secy.

and Published by the Controller of Publications, Delhi-110054.

GORAKHA NATH YADAVA

Provisions this notification answers to

Read out of the instrument itself: an enabling provision is one it says it was made under, which is the power it rests on. The rest it names without resting on.

Other instruments under the same Act

All of the The Environment (Protection) Act, 1986

Source and method. Compiled from the enactments of Parliament and of the State legislatures as published on India Code, and republished together with commentary and other original matter under section 52(1)(q)(ii) of the Copyright Act, 1957. Structured, cross-referenced and maintained by eCourtsIndia. Recorded by India Code; the text, where shown, is what its own document carried. This page is not a substitute for legal advice.