Notification, 2011
A notification made under the The Electricity Act, 2003.
Made under The Electricity Act, 2003.
Text
Reproduced from the document India Code holds for this instrument. The Gazette prints Hindi and English side by side and this is the English; the Department's own PDF remains the authority.
[Extract from the Chd. Admn. Gaz. (Extra.), dated the 10th August, 2011]
CHANDIGARH ADMINISTRATION
ENGINEERING DEPARTMENT
(ELECTRICITY WING) Notification No. G1/2011/04.—In exercise of the powers conferred by Section 152 of the Electricity Act, 2003 read with notification dated 22nd June, 2004 issued by the Government of India, Ministry of Home Affairs, New Delhi, the Administrator, Union Territory, Chandigarh is pleased to authorize the following officers for compounding of offences relating to theft of electricity as prescribed under
Section 152 of the Electricity Act, 2003 by various categories of consumers. The compounding fee/ rates shall be as per the details mentioned against each category of consumer in the table given below :— Sr. Category of Officers Authorized for Rate for Compounding
No. Service/Consumer . Compounding
1. Domestic supply (up to 500 KW of sanctioned load) Sub Divisional Officer of respective area Rs. 4,000 per KW or part thereof on the basis of actual load found at site at the time of inspection/ checking.
(up to 500 KW of sanctioned load) Sub Divisional Officer of respective area Rs. 2,000 per BHP or part thereof on the basis of actual load found at site at the time of inspection/ checking.
(up to 500 KW of sanctioned load) Sub Divisional Officer of respective area Rs. 10,000 per KW or part thereof on the basis of actual load found at site at the time of inspection/ checking.
4. Bulk suppiy and Small Power Supply (up to 500 KW of sanctioned load) Sub Divisional Officer of respective area \ Rs. 4,000 per KW or part thereof on the basis of actual load found at site at the time of inspection/ checking.
5. Domestic supply (Above 500 KW of sanctioned load) Executive Engineer of the respective area Rs. 4,000 per KW or part thereof on the basis of actual load found at site at the time of inspection/ checking.
6. Agriculture supply (Above 500 KW of sanctioned load) Executive Engineer of the respective area Rs. 2,000 per BHP or part thereof on the basis of actual load found at site at the time of inspection/ checking.
person or consumer.
Sr.
No.
Category of Officers Authorized for Compounding Rate for Compounding (Above 500 KW of sanctioned load) Executive Engineer of the - respective area Rs. 10,000 per KW or part thereof on the basis of actual load found at site at the time of inspection/ , checking. *
8. Bulk supply (Above 500 KW of sanctioned load) Executive Engineer of the respective area Rs. 4,000 per KW or part ’ thereof on the basis of actual load found at site at the time of inspection/ checking.
9. Industrial
(a) Medium supply Executive Engineer Rs. 20,000 per KW or part thereof on the basis of actual load found at site at the time of inspection/ checking.
Note.—The compounding of an offence under Section 152(1) shall be allowed only once for any For and on behalf of Administrator, U.T., Chandigarh.
(Sd.) . . ., Secretary Engineering, U.T., Chandigarh.
Provisions this notification answers to
Read out of the instrument itself: an enabling provision is one it says it was made under, which is the power it rests on. The rest it names without resting on.
Other instruments under the same Act
Source and method. Compiled from the enactments of Parliament and of the State legislatures as published on India Code, and republished together with commentary and other original matter under section 52(1)(q)(ii) of the Copyright Act, 1957. Structured, cross-referenced and maintained by eCourtsIndia. Recorded by India Code; the text, where shown, is what its own document carried. This page is not a substitute for legal advice.