Power of revocation and modification of permission for development
Section 30 of the Ajmer Development Authority Act, 2013 deals with power of revocation and modification of permission for development. If it appears to the Authority that it is expedient, having regard to the Plan prepared or under preparation, that any permission to develop land granted under this Act or any other law should be revoked or modified, the Authority may after giving the person concerned an opportunity of being heard a The Act was enacted on 08 Aug 2013.
(1) If it appears to the Authority that it is expedient, having regard to the Plan prepared or under preparation, that any permission to develop land granted under this Act or any other law should be revoked or modified, the Authority may after giving the person concerned an opportunity of being heard against such revocation or modification, by order, revoke or modify the permission to such extent as appears to it to be necessary :
Provided that -
(a) where the development relates to the carrying out of any building or other operation, no such order shall affect such of the operations as have been previously carried out or shall be passed after these operations have substantially progressed or have been completed ;
(b) where the development relates to a change of use of land, no such order shall be passed at any time after the change has taken place:
Provided further that where the revocation or modification of the permission is necessary in public interest, the provisions of the first proviso shall not apply.
(2) Where permission is revoked or modified by an order made under sub-section (1) and any owner claims within the time and in the manner prescribed, compensation for the expenditure incurred in carrying out the development in accordance with such permission which has been rendered abortive by the revocation or modification, the Authority shall, after giving the owner reasonable opportunity of being heard by the office, appointed by it in this behalf and after considering his report assess and offer reasonable compensation to the owner.
(3) If the owner does not accept the compensation and gives notice within thirty days of his refusal to accept, the Authority shall refer the matter for the adjudication of the Tribunal and the decision of the Tribunal shall be final and be binding on the owner and the Authority.
Section 30, The Ajmer Development Authority Act, 2013 (Act 39 of 2013).
Cross-references
Extracted from the operative text of the enactments themselves. Every destination below exists in our corpus.
Referred to by 1
Questions about Section 30
What does Section 30 of the Ajmer Development Authority Act deal with?
Section 30 of the Ajmer Development Authority Act is headed "Power of revocation and modification of permission for development". If it appears to the Authority that it is expedient, having regard to the Plan prepared or under preparation, that any permission to develop land granted under this Act or any other law should be revoked or modified, the Authority may after giving the person concerned an opportunity of being heard a
How do I find court cases under Section 30 of the Ajmer Development Authority Act?
In judgments and charge sheets this section is written several ways, and each form finds a different set of orders. These search the full text of every order eCourtsIndia holds, best matches first: Ajmer Development Authority Act 30, section 30 Ajmer Development Authority Act, section 30 of the Ajmer Development Authority Act. Each opens the full list of orders on eCourtsIndia, where it can be narrowed by court, year and outcome.
What should I read with Section 30 of the Ajmer Development Authority Act, and has it changed?
1 other provision in this corpus refers back to it.
When was Section 30 of the Ajmer Development Authority Act enacted?
Section 30 of the Ajmer Development Authority Act, cited as Ajmer Development Authority Act 30, was enacted on 08 Aug 2013 as Act 39 of 2013. It is in force as at the date shown on this page.
Other sections of this Act
- 96. Dissolution of the Urban Improvement Trust, Ajmer and savings1245 words
- 67. Encroachment or obstruction upon public land835 words
- 2. Definitions750 words
- 39. Making and contents of Projects and Schemes724 words
- 4. Composition of the Ajmer Development Authority667 words
- 21. Civic Survey and preparation of Master Development Plan666 words
Source and method. Compiled from the enactments of Parliament and of the State legislatures as published on India Code, and republished together with commentary and other original matter under section 52(1)(q)(ii) of the Copyright Act, 1957. Structured, cross-referenced and maintained by eCourtsIndia. Text as in force on 20 Oct 2026. This page is not a substitute for legal advice.