Section33
The Ajmer Development Authority Act, 2013

Power to stop unauthorised development

In force Act 39 of 2013 As on 19 Oct 2026

Act 39 of 2013 Enacted 08 Aug 2013 Cited by 1 provision

Section 33 of the Ajmer Development Authority Act, 2013 deals with power to stop unauthorised development. Where any development of land as indicated in sub-section (1) of section 31 is being carried out but has not been completed, the Authority may serve on the owner and the person carrying out the development, a notice requiring the development of land to be discontinued from the time of the service of The Act was enacted on 08 Aug 2013.

(1) Where any development of land as indicated in sub-section (1) of section 31 is being carried out but has not been completed, the Authority may serve on the owner and the person carrying out the development, a notice requiring the development of land to be discontinued from the time of the service of the notice, and thereupon, the provisions of sub-sections (3),(4),(5) and (6) of section 32 shall, so far as may be applicable, apply in relation to such notice, as they apply in relation to notice under section 32.

(2) Any person, who continues to carry out the development of land, whether for himself or on behalf of the owner or any other person, after such notice has been served shall, on conviction, be punished with fine which may extend to five thousand rupees and when the non compliance is a continuing one, with a further fine which may extend to five hundred rupees for every day after the date of the service of the notice during which the non compliance has continued or continues.

(3) Notwithstanding anything contained in this chapter, where any person continues to carry out unauthorised development after receiving a notice under sub-section (1), the Authority or any officer authorised by it in this behalf, shall, in addition to any prosecution or other proceedings or action that may be initiated under this Act, have the power to require any Police Officer to remove the person by whom the erection of the building has been continued and all his assistants and workmen from the place of the unauthorised development within such time as may be specified in the requisition and such Police Officer shall comply with the requisition accordingly. In addition to such removal of persons the Authority may also confiscate such construction materials, tools, etc. which such person was using for unauthorised development. After a requisition order under sub-section (3) has been complied with, any person or his assistants and workmen subsequently continuing unauthorised development shall, on conviction, be punishable under section 66 of this Act, in addition to the action under sub-section (3).

(4) No compensation shall be claimed by any person for any damage which he may sustain in consequence of the discontinuation of the unauthorised development under this Act.

Section 33, The Ajmer Development Authority Act, 2013 (Act 39 of 2013).

Cross-references

Extracted from the operative text of the enactments themselves. Every destination below exists in our corpus.

Questions about Section 33

What does Section 33 of the Ajmer Development Authority Act deal with?

Section 33 of the Ajmer Development Authority Act is headed "Power to stop unauthorised development". Where any development of land as indicated in sub-section (1) of section 31 is being carried out but has not been completed, the Authority may serve on the owner and the person carrying out the development, a notice requiring the development of land to be discontinued from the time of the service of

How do I find court cases under Section 33 of the Ajmer Development Authority Act?

In judgments and charge sheets this section is written several ways, and each form finds a different set of orders. These search the full text of every order eCourtsIndia holds, best matches first: Ajmer Development Authority Act 33, section 33 Ajmer Development Authority Act, section 33 of the Ajmer Development Authority Act. Each opens the full list of orders on eCourtsIndia, where it can be narrowed by court, year and outcome.

What should I read with Section 33 of the Ajmer Development Authority Act, and has it changed?

Its own text turns on section 31 (Penalty for unauthorised development for use otherwise than in conformity with the Plan), section 32 (Power to require removal of unauthorised development), section 66 (Penalty for disobedience of requisition and furnishing false information, etc), so none of them can safely be read on its own. 1 other provision in this corpus refers back to it.

When was Section 33 of the Ajmer Development Authority Act enacted?

Section 33 of the Ajmer Development Authority Act, cited as Ajmer Development Authority Act 33, was enacted on 08 Aug 2013 as Act 39 of 2013. It is in force as at the date shown on this page.

Other sections of this Act

Source and method. Compiled from the enactments of Parliament and of the State legislatures as published on India Code, and republished together with commentary and other original matter under section 52(1)(q)(ii) of the Copyright Act, 1957. Structured, cross-referenced and maintained by eCourtsIndia. Text as in force on 19 Oct 2026. This page is not a substitute for legal advice.