Section35
The Indian Contract Act, 1872

When contracts become void which are contingent on happening of specified event within fixed time . When contracts may be enforced, which are contingent on specified event not happening within fixed time

In force From 01 Sep 1872 Act 9 of 1872 As on 15 Oct 2026

Act 9 of 1872 Ministry Law and Justice Enacted 25 Apr 1872 In force 01 Sep 1872

Section 35 of the Indian Contract Act, 1872 deals with when contracts become void which are contingent on happening of specified event within fixed time . When contracts may be enforced, which are contingent on specified event not happening within fixed time. Contingent contracts to do or not to do anything if a specified uncertain event happens within a fixed time become void if, at the expiration of the time fixed, such event has not happened, or if, before the time fixed, such event becomes impossible. The Act came into force on 01 Sep 1872.

Contingent contracts to do or not to do anything if a specified uncertain event happens within a fixed time become void if, at the expiration of the time fixed, such event has not happened, or if, before the time fixed, such event becomes impossible.

When contracts may be enforced, which are contingent on specified event not happening within fixed time.—Contingent contracts to do or not to do anything, if a specified uncertain event does not happen within a fixed time may be enforced by law when the time fixed has expired and such event has not happened or, before the time fixed has expired, if it becomes certain that such event will not happen.

Illustrations

(a) A promises to pay B a sum of money if a certain ship returns within a year. The contract may be enforced if the ship returns within the year, and becomes void if the ship is burnt within the year.

(b) A promises to pay B a sum of money if a certain ship does not return within a year. The contract may be enforced if the ship does not return within the year, or is burnt within the year.

Section 35, The Indian Contract Act, 1872 (Act 9 of 1872).

Questions about Section 35

What does Section 35 of the Indian Contract Act deal with?

Section 35 of the Indian Contract Act is headed "When contracts become void which are contingent on happening of specified event within fixed time . When contracts may be enforced, which are contingent on specified event not happening within fixed time". Contingent contracts to do or not to do anything if a specified uncertain event happens within a fixed time become void if, at the expiration of the time fixed, such event has not happened, or if, before the time fixed, such event becomes impossible.

How do I find court cases under Section 35 of the Indian Contract Act?

In judgments and charge sheets this section is written several ways, and each form finds a different set of orders. These search the full text of every order eCourtsIndia holds, best matches first: Contract Act 35, section 35 Contract Act, section 35 of the Indian Contract Act. People searching for it also type indian contract act section 35. Each opens the full list of orders on eCourtsIndia, where it can be narrowed by court, year and outcome.

When did Section 35 of the Indian Contract Act come into force?

Section 35 of the Indian Contract Act, cited as Contract Act 35, came into force on 01 Sep 1872, having been enacted on 25 Apr 1872. It is in force as at the date shown on this page.

Other sections of this Act

Source and method. Compiled from the enactments of Parliament and of the State legislatures as published on India Code, and republished together with commentary and other original matter under section 52(1)(q)(ii) of the Copyright Act, 1957. Structured, cross-referenced and maintained by eCourtsIndia. Text as in force on 15 Oct 2026. This page is not a substitute for legal advice.