Definitions
Section 2 of the Electricity Act, 2003 deals with definitions. this Act, unless the context otherwise requires,-- (1)"Appellate Tribunal" means the Appellate Tribunal for Electricity established under section 110; The Act came into force on 10 Jun 2003.
this Act, unless the context otherwise requires,--
(1) "Appellate Tribunal" means the Appellate Tribunal for Electricity established under section 110;
(2) "appointed date" means such date as the Central Government may, by notification, appoint;
(3) "area of supply" means the area within which a distribution licensee is authorised by his licence to supply electricity;
(4) "Appropriate Commission" means the Central Regulatory Commission referred to in sub-section (1) of section 76 or the State Regulatory Commission referred to in section 82 or the Joint Commission referred to in section 83, as the case may be;
(5) "Appropriate Government" means,--
(a) the Central Government,--
(i) in respect of a generating company wholly or partly owned by it;
(ii) in relation to any inter-State generation, transmission, trading or supply of electricity and with respect to any mines, oil-fields, railways, national highways, airports, telegraphs, broadcasting stations and any works of defence, dockyard, nuclear power installations;
(iii) in respect of National Load Despatch Centre and Regional Load Despatch Centre;
(iv) in relation to any works or electric installation belonging to it or under its control;
(b) in any other case, the State Government, having jurisdiction under this Act;
(6) "Authority" mean the Central Electricity Authority referred to in sub-section (1) of section 70;
(7) "Board" means a State Electricity Board, constituted before the commencement of this Act, under sub-section (1) of section 5 of the Electricity (Supply) Act, 1948 (54 of 1948);
(8) "Captive generating plant" means a power plant set up by any person to generate electricity primarily for his own use and includes a power plant set up by any co-operative society or association of persons for generating electricity primarily for use of members of such co-operative society or association;
(9) "Central Commission" means the Central Electricity Regulatory Commission referred to in sub-section (1) of section 76;
(10) "Central Transmission Utility" means any Government company which the Central Government may notify under sub-section (1) of section 38;
(11) "Chairperson" means the Chairperson of the Authority or Appropriate Commission or the Appellate Tribunal, as the case may be;
(12) "Cogeneration" means a process which simultaneously produces two or more forms of useful energy (including electricity);
(13) "company" means a company formed and registered under the Companies Act, 1956 (1 of 1956) and includes any body corporate under a Central, State or Provincial Act;
(14) "conservation" means any reduction in consumption of electricity as a result of increase in the efficiency in supply and use of electricity;
(15) "consumer" means any person who is supplied with electricity for his own use by a licensee or the Government or by any other person engaged in the business of supplying electricity to the public under this Act or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity with the works of a licensee, the Government or such other person, as the case may be;
(16) "dedicated transmission lines" means any electric supply-line for point to point transmission which are required for the purpose of connecting electric lines or electric plants of a captive generating plant referred to in section 9 or generating station referred to in section 10 to any transmission lines or sub-stations, or generating stations, or the load centre, as the case may be;
(17) "distribution licensee" means a licensee authorised to operate and maintain a distribution system for supplying electricity to the consumers in his area of supply;
(18) "distributing main" means the portion of any main with which a service line is, or is intended to be, immediately connected;
(19) "distribution system" means the system of wires and associated facilities between the delivery points on the transmission lines or the generating station connection and the point of connection to the installation of the consumers;
(20) "electric line" means any line which is used for carrying electricity for any purpose and includes--
(a) any support for any such line, that is to say, any structure, tower, pole or other thing in, on, by or from which any such line is, or may be, supported, carried or suspended; and
(b) any apparatus connected to any such line for the purpose of carrying electricity;
(21) "Electrical Inspector" means a person appointed as such by the Appropriate Government under sub-section (1) of section 162 and also includes Chief Electrical Inspector;
(22) "electrical plant" means any plant, equipment, apparatus or appliance or any part thereof used for, or connected with, the generation, transmission, distribution or supply of electricity but does not include--
(a) an electric line; or
(b) a meter used for ascertaining the quantity of electricity supplied to any premises; or
(c) an electrical equipment, apparatus or appliance under the control of a consumer;
(23) "electricity" means electrical energy--
(a) generated, transmitted, supplied or traded for any purpose; or
(b) used for any purpose except the transmission of a message;
(24) "Electricity Supply Code" means the Electricity Supply Code specified under section 50;
(25) "electricity system" means a system under the control of a generating company or licensee, as the case may be, having one or more--
(a) generating stations; or
(b) transmission lines; or
(c) electric lines and sub-stations,
and when used in the context of a State or the Union, the entire electricity system within the territories thereof;
(26) "electricity trader" means a person who has been granted a licence to undertake trading in electricity under section 12;
(27) "franchisee" means a persons authorised by a distribution licensee to distribute electricity on its behalf in a particular area within his area of supply;
(28) "generating company" means any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person, which owns or operates or maintains a generating station;
(29) "generate" means to produce electricity from a generating station for the purpose of giving supply to any premises or enabling a supply to be so given;
(30) "generating station" or "station" means any station for generating electricity, including any building and plant with step-up transformer, switch-gear, switch yard, cables or other appurtenant equipment, if any, used for that purpose and the site thereof; a site intended to be used for a generating station, and any building used for housing the operating staff of a generating station, and where electricity is generated by water-power, includes penstocks, head and tail works, main and regulating reservoirs, dams and other hydraulic works, but does not in any case include any sub-station;
(31) "Government company" shall have the meaning assigned to it in section 617 of the Companies Act, 1956 (1 of 1956);
(32) "grid" means the high voltage backbone system of inter-connected transmission lines, sub-station and generating plants;
(33) "Grid Code" means the Grid Code specified by the Central Commission under clause (h) of sub-section (1) of section 79;
(34) "Grid Standards" means the Grid Standards specified under clause (d) of section 73 by the Authority;
(35) "high voltage line" means an electric line or cable of a nominal voltage as may be specified by the Authority from time to time;
(36) "inter-State transmission system" includes--
(i) any system for the conveyance of electricity by means of main transmission line from the territory of one State to another State;
(ii) the conveyance of electricity across the territory of an intervening State as well as conveyance within the State which is incidental to such inter-State transmission of electricity;
(iii) the transmission of electricity within the territory of a State on a system built, owned, operated, maintained or controlled by a Central Transmission Utility;
(37) 'intra-State transmission system' means any system for transmission of electricity other than an inter-State transmission system;
(38) 'licence" means a licence granted under section 14;
(39) "licensee" means a person who has been granted a licence under section 14;
(40) "line" means any wire, cable, tube, pipe, insulator, conductor or other similar thing (including its casing or coating) which is designed or adapted for use in carrying electricity and includes any line which surrounds or supports, or is surrounded or supported by or is installed in close proximity to, or is supported, carried or suspended in association with, any such line;
(41) "local authority" means any Nagar Panchayat, Municipal Council, municipal corporation, Panchayat constituted at the village, intermediate and district levels, body of port commissioners or other authority legally entitled to, or entrusted by the Union or any State Government with, the control or management of any area or local fund;
(42) "main" means any electric supply-line through which electricity is, or is intended to be, supplied;
(43) "Member" means the Member of the Appropriate Commission or Authority or Joint Commission, or the Appellate Tribunal, as the case may be, and includes the Chairperson of such Commission or Authority or Appellate Tribunal;
(44) "National Electricity Plan" means the National Electricity Plan notified under sub-section (4) of section 3;
(45) "National Load Despatch Centre" means the Centre established under sub-section (1) of section 26;
(46) "notification" means notification published in the Official Gazette and the expression "notify" shall be construed accordingly;
(47) "open access" means the non-discriminatory provision for the use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by the Appropriate Commission;
(48) "overhead line" means an electric line which is placed above the ground and in the open air but does not include live rails of a traction system;
(49) "person" shall include any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person;
(50) "power system" means all aspects of generation, transmission, distribution and supply of electricity and includes one or more of the following, namely:--
(a) generating stations;
(b) transmission or main transmission lines;
(c) sub-stations;
(d) tie-lines;
(e) load despatch activities;
(f) mains or distribution mains;
(g) electric supply-lines;
(h) overhead lines;
(i) service lines;
(j) works;
(51) "premises" includes any land, building or structure;
(52) "prescribed" means prescribed by rules made by the Appropriate Government under this Act;
(53) "public lamp" means an electric lamp used for the lighting of any street;
(54) "real time operation" means action to be taken at a given time at which information about the electricity system is made available to the concerned Load Despatch Centre;
(55) "Regional Power Committee" means a committee established by resolution by the Central Government for a specified region for facilitating the integrated operation of the power systems in that region;
(56) "Regional Load Despatch Centre" means the Centre established under sub-section (1) of section 27;
(57) "regulations" means regulations made under this Act;
(58) "repealed laws" means the Indian Electricity Act, 1910 (9 of 1910), the Electricity (Supply) Act, 1948 (54 of 1948) and the Electricity Regulatory Commissions Act, 1998 (14 of 1998) repealed by section 185;
(59) "rules" means rules made under this Act;
(60) "Schedule" means the Schedule to this Act;
(61) "service-line" means any electric supply-line through which electricity is, or is intended to be, supplied--
(a) to a single consumer either from a distributing main or immediately from the Distribution Licensee's premises; or
(b) from a distributing main to a group of consumers on the same premises or on contiguous premises supplied from the same point of the distributing main;
(62) 'specified" means specified by regulations made by the Appropriate Commission or the Authority, as the case may be, under this Act;
(63) "stand alone system" means the electricity system set-up to generate power and distribute electricity in a specified area without connection to the grid;
(64) "State Commission" means the State Electricity Regulatory Commission constituted under sub-section (1) of section 82 and includes a Joint Commission constituted under sub-section (1) of section 83;
(65) "State Grid Code" means the State Grid Code specified under clause (h) of sub-section (1) of section 86;
(66) "State Load Despatch Centre" means the centre established under sub-section (1) of section 31;
(67) "State Transmission Utility" means the Board or the Government company specified as such by the State Government under sub-section (1) of section 39;
(68) "street" includes any way, road, lane, square, court, alley, passage or open space, whether a thoroughfare or not, over which the public have a right of way, and also the roadway and footway over any public bridge or causeway;
(69) "sub-station" means a station for transforming or converting electricity for the transmission or distribution thereof and includes transformers converters, switch-gears, capacitors, synchronous condensers, structures, cable and other appurtenant equipment and any buildings used for that purpose and the site thereof;
(70) "supply", in relation to electricity, means the sale of electricity to a licensee or consumer;
(71) "trading" means purchase of electricity for resale thereof and the expression "trade" shall be construed accordingly;
(72) "transmission lines means all high pressure cables and overhead lines (not being an essential part of the distribution system of a licensee) transmitting electricity from a generating station to another generating station or a sub-station, together with any step-up and step-down transformers, switch-gear and other works necessary to and used for the control of such cables or overhead lines, and such buildings or part thereof as may be required to accommodate such transformers, switch-gear and other works;
(73) "transmission licensee" means a licensee authorised to establish or operate transmission lines;
(74) "transmit" means conveyance of electricity by means of transmission lines and the expression "transmission" shall be construed accordingly;
(75) "utility" means the electric lines or electrical plant, and includes all lands, buildings, works and materials attached thereto belonging to any person acting as a generating company or licensee under the provisions of this Act;
(76) "wheeling" means the operation whereby the distribution system and associated facilities of a transmission licensee or distribution licensee, as the case may be, are used by another person for the conveyance of electricity on payment of charges to be determined under section 62;
(77) "works" includes electric line, and any building, plant, machinery, apparatus and any other thing of whatever description required to transmit, distribute or supply electricity to the public and to carry into effect the objects of a licence or sanction granted under this Act or any other law for the time being in force.
Section 2, The Electricity Act, 2003 (Act 36 of 2003).
Cross-references
Extracted from the operative text of the enactments themselves. Every destination below exists in our corpus.
This section refers to
- s. 3 National Electricity Policy and Plan
- s. 9 Captive generation
- s. 10 Duties of generating companies
- s. 12 Authorised persons to transmit, supply, etc., electricity
- s. 14 Grant of licence
- s. 26 National Load Despatch Centre
- s. 27 Constitution of Regional Load Despatch Centre
- s. 31 Constitution of State Load Despatch Centres
- s. 38 Central Transmission Utility and functions
- s. 39 State Transmission Utility and functions
- s. 50 The Electricity supply code
- s. 62 Determination of tariff
- s. 70 Constitution, etc., of Central Electricity Authority
- s. 73 Functions and duties of Authority
- s. 76 Constitution of Central Commission
- s. 79 Functions of Central Commission
- s. 82 Constitution of State Commission
- s. 83 Joint Commission
- s. 86 Functions of State Commission
- s. 110 Establishment of Appellate Tribunal
- s. 162 Appointment of Chief Electrical Inspector and Electrical Inspector
- s. 185 Repeal and saving
- Electricity (Supply) Act s. 5
Referred to by 1
Related judgements & precedents
These are some judgments that construed this section, and hold precedence value. They hold authority on how to read, interpret and use this section.
-
Vidarbha Industries Power Limited vs Axis Bank Limited
Court's Decision & Legal Precedent
Section 7(5)(a) of the Insolvency and Bankruptcy Code 2016 confers discretionary power on the Adjudicating Authority (NCLT) to admit or reject an application for Corporate Insolvency Resolution Process filed by a financial creditor, even when default is established and the application is complete. The NCLT must apply its mind to relevant factors including the feasibility of initiating CIRP against the corporate debtor, the impact of pending regulatory appeals and awards, and the overall financial health and viability of the corporate debtor under its existing management. The existence of a financial debt and default in payment thereof only gives the financial creditor the right to apply for initiation of CIRP; it does not mandate automatic admission. The NCLT may exercise its discretion to keep the admission of the application in abeyance or reject it if the corporate debtor demonstrates that a substantial award or decree in its favor is pending, which if realized would exceed the debt claimed by the financial creditor.
On this section: Definition of Generating Company
-
Power Grid Corpn. of India vs Century Textiles&inds. LTD & ORS
Court's Decision & Legal Precedent
A Central Transmission Utility, upon being conferred the powers of Telegraph Authority under Section 164 of the Electricity Act, 2003, has the legal authority to lay high-voltage electricity transmission lines across privately leased land without the consent of the lessee, as the Indian Telegraph Act, 1885 prioritizes unobstructed access for telegraph and electricity transmission lines in the larger public interest. The requirement of prior consent under Rule 3 of the Works of Licensees Rules, 2006 does not apply to such utilities. Compensation for any damage caused by the exercise of these powers is determined by the District Judge under Section 16 of the Indian Telegraph Act, 1885, not by administrative authorities. The action of the utility is not arbitrary merely because the cost of realignment is lower than the financial loss to the private party, as the court must consider the stage of project completion, technical feasibility, and the national importance of the infrastructure project.
On this section: Definition of 'Appropriate Government' - Central Government is the Appropriate Government for Central Transmission Utility
-
J. K. Tyre & Industries LTD vs Rajasthan Electricity Regulatory Commn
Court's Decision & Legal Precedent
The Rajasthan Electricity Regulatory Commission has statutory power under Section 86(1)(e) read with Section 181 of the Electricity Act 2003 to impose renewable energy purchase obligations on captive power plants and open access consumers located in the area of distribution licensee, as the term 'total consumption in the area of distribution licensee' includes consumption from all sources within that geographical area. Such obligations, being designed to achieve constitutional mandates under Articles 21, 48A, and 51A(g) of the Constitution and to promote renewable energy as a matter of public policy, do not violate the de-licensing principle of the Act nor do they infringe fundamental rights under Articles 14 or 19(1)(g) of the Constitution. The surcharge imposed for non-compliance is a valid regulatory measure under Section 86(1)(g) and Sections 142, 147 of the Act, representing a compensatory mechanism based on the polluter-pays principle, not an unauthorized tax under Article 265.
On this section: Definition interpreted to include geographical territory where distribution licensee is authorized to supply electricity, encompassing captive power plants and open access consumers connected to distribution network
The holding above is the ratio decidendi as extracted from the judgment by eCourts India, reproduced unaltered — it is a rendering of the court's reasoning, not a substitute for its words. Read the order itself before relying on it.
Made under this section, and citing it
6 instruments state that it was made under this provision — the power to make it comes from here, so a change to any of them changes what this section requires in practice. Newest first.
- Uttar Pradesh Electricity Regulatory Commission Power System Development Fund Regulations, 2023Regulation 2023
- Standard of Performance Regulations, 2015Regulation 2015
- The Joint Electricity Regulatroy Commission for the state of Goa and UT(Standard of Performance for Distribution licensees)Regulation,2015Regulation 2015
- JERC Notification dated 11.08.2011Notification 2011
- Chhattisgarh State Electricity Regulatory Commission (Licence) Regulations, 2004. Dt. 07.12.2004Regulation 2004
- Joint Electricity Regulatory Commission” (Distribution Code) Regulations, 2010.Regulation 1933
Another 13 instruments name this provision in its title or its text without being made under it.
- CSERC (Redressal of Grievances of the Consumers) Regulations, 2023.Regulation 2023
- Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023Regulation 2023
- Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023.Regulation 2023
- The Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023Regulation 2023
- UP Electricity Regulatory Commission (Consumer Grievance Redressal Forum) Regulations, 2022Regulation 2022
- Central Electricity Authority (Technical Standards for Communication System in Power System Operation) Regulations, 2020Regulation 2020
- Delhi Electricity Regulatory Commission (Forum for Redressal of Grievances of the Consumers and Ombudsman) Regulations, 2018Regulation 2018
- Delhi Electricity Regulatory Commission (Demand Side Management) Regulations, 2014Regulation 2014
- JERC Notification dated 25.03.2013Notification 2013
- The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012Regulation 2012
- The Himachal Pradesh Electricity Regulatory Commission (Demand Side Management) Regulations, 2011Regulation 2011
- JERC Notification dated 20.05.2010Notification 2010
- The Electricity Rules, 2005Rule 2005
Questions about Section 2
What have the courts held on Section 2 of the Electricity Act?
Vidarbha Industries Power Limited vs Axis Bank Limited (12 Jul 2022) is the leading judgment on this section among those set out below: Definition of Generating Company. Another 2 judgments on this section are set out below, all of them from the Supreme Court. They run from 2015 to 2022.
How do I find court cases under Section 2 of the Electricity Act?
In judgments and charge sheets this section is written several ways, and each form finds a different set of orders. These search the full text of every order eCourtsIndia holds, best matches first: Electricity Act 2003 2, section 2 Electricity Act 2003, section 2 of the Electricity Act. Each opens the full list of orders on eCourtsIndia, where it can be narrowed by court, year and outcome. 3 reported judgments on this section are set out on this page, beginning with Vidarbha Industries Power Limited vs Axis Bank Limited (12 Jul 2022).
What should I read with Section 2 of the Electricity Act, and has it changed?
Its own text turns on section 3 (National Electricity Policy and Plan), section 9 (Captive generation), section 10 (Duties of generating companies), section 12 (Authorised persons to transmit, supply, etc., electricity), and on 19 further provisions, so none of them can safely be read on its own. 1 other provision in this corpus refers back to it. The rules and notifications made under it are where it actually bites, and there are 6: most recently Uttar Pradesh Electricity Regulatory Commission Power System Development Fund Regulations, 2023 (2023), then Standard of Performance Regulations, 2015 (2015), and 4 more.
When did Section 2 of the Electricity Act come into force?
Section 2 of the Electricity Act, cited as Electricity Act 2003 2, came into force on 10 Jun 2003, having been enacted on 26 May 2003. It is in force as at the date shown on this page.
Other sections of this Act
Source and method. Compiled from the enactments of Parliament and of the State legislatures as published on India Code, and republished together with commentary and other original matter under section 52(1)(q)(ii) of the Copyright Act, 1957. Structured, cross-referenced and maintained by eCourtsIndia. Text as in force on 14 Oct 2026. This page is not a substitute for legal advice.